Project
Challenges
Design of a 12MW standalone power supply for a 3,800 unit remote workcamp for the construction of a 7.5 million ton per annum LNG plant, including 60 laundry facilities and a 1,500 seat commercial kitchen.
Goals & Objectives
The primary objective was to develop a cost effective and reliable electricity supply for a 24-hour power supply to supply continuous power for the 3,800 unit construction workcamp with full town utility water and support services.
Solutions
Service provided
Power Generation System Design
Develop a site Load Duration Curve
Techno-Economic Modelling to establish Business Case
Project Management
Measurement and Verification of Energy Saving
Results and Benefits
Financial Results
25% IRR
Capital Investment $25M
Annual Gross Revenue $8M
75% COGS
Technologies applied
Power Generation
Meter Technology
Online Electricity Dashboard
ESG Impact
8,000 ton CO2 savings
32 jobs created

Project Location
Onslow Western Australia, Australia