Chevron AUS, Wheatstone, Power Generation, AUS

Diesel Power Station and Energy Management

Location:

Status:

Sector:

Onslow Western Australia, Australia

Buildings and Construction

Completed

Project

Challenges

  • Design of a 12MW standalone power supply for a 3,800 unit remote workcamp for the construction of a 7.5 million ton per annum LNG plant, including 60 laundry facilities and a 1,500 seat commercial kitchen.

Goals & Objectives

  • The primary objective was to develop a cost effective and reliable electricity supply for a 24-hour power supply to supply continuous power for the 3,800 unit construction workcamp with full town utility water and support services.

Solutions

Service provided

  • Power Generation System Design

  • Develop a site Load Duration Curve

  • Techno-Economic Modelling to establish Business Case

  • Project Management

  • Measurement and Verification of Energy Saving

Results and Benefits 

Financial Results

  • 25% IRR

  • Capital Investment $25M

  • Annual Gross Revenue $8M

  • 75% COGS

Technologies applied

  • Power Generation

  • Meter Technology

  • Online Electricity Dashboard

ESG Impact

  • 8,000 ton CO2 savings

  • 32 jobs created