Project
Challenges
Design and construct a range of energy efficiency and energy management measures in the support services for the plastics factory; compressed air, ground plastics, lighting, ventilation and HVAC.
Goals & Objectives
Gundle Plastics set a goal to reduce total electricity use by 20% by implementing energy management plan on all support services of their plastics factory.
Solutions
Service provided
Energy Efficiency Design
Energy Management System Design
Techno-Economic Modelling to establish Business Case
Project Management
Operation and Maintenance Contract
Measurement and Verification of Energy Saving
Results and Benefits
Financial Results
35% IRR
Capital Investment $0.15M
Annual Gross Revenue $0.7M
5% COGS
Technologies applied
Voltage Optimiser
Ventilation on Demand
HVAC Optimisation
Compressed Air Pressure Reduction
Super Efficient LED Lighting
Energy Management Scheduling
Meter Technology
Online Electricity Dashboard
ESG Impact
200 ton CO2 savings
3 jobs created

Project Location
Johannesburg, South Africa