Palabora Mining Company, SO2 Blower, South Africa

SO2 Blower Optimization Project

Location:

Status:

Sector:

Phalaborwa, South Africa

Mining and Heavy Industry

Completed

Project

Challenges

  • The 6MW SO2 Blower operate 24/7 to draw exhaust air from the Copper Converter Blows which operate in a batch process. The annual coal cost to operate the SO2 blower is US3M p.a.

Goals & Objectives

  • The primary objective was to design and implement an energy efficient SO2 blower system with a target 75% energy saving reduction by matching operation of the 6MW blower motor only when then copper converter operates which requires the turning off of the motor during non-batch converter processes.

Solutions

Service provided

  • Design of an Energy Efficient SO2 Blower

  • Energy Management Software & IT Energy Modelling

  • Techno-Economic Modelling to establish the Business Case

  • Project Management

  • Measurement and Verification of Energy Saving

Results and Benefits 

Financial Results

  • 40% IRR

  • Capital Investment $5M

  • Annual Gross Savings $2.2M

  • 2.5% COGS

Technologies applied

  • Induction Motor

  • VSD Operation

  • Equipment Optimization

  • Meter Technology

  • Online Electricity Dashboard

ESG Impact

  • 35,000 tons CO2 savings

image.png