Project
Challenges
Integrate existing cassava processing with biogas power generation on a win-win basis.
Introduction and realization of a new standard level of biogas generation
Confirmation with UNFCCC protocol standards
Goals & Objectives
Replace fossil fuel with a renewable energy efficiently and cost-effective
Ensure sustainable wastewater quality improvement to meet legal standards
Solutions
Service provided
Conceptualization, feasibility studies, implementation and operations
Project Management and Corporate Management
Carbon credit application under CDM protocol of UNFCCC
Results and Benefits
Financial Results
25% reduction of fuel costs for cassava processing
20% IRR
Capital Investment €1.6 million
Technologies applied
Power Generation (conversion of biogas into thermal energy)
Biogas Digester (Anaerobic lagoon of 16000 m3, with 90% efficiency)
Biogas Treatment
Wastewater treatment
ESG Impact
9901 metric ton CO2 equivalent reduction per annum
3 permanent jobs created
Transfer of Covered High Energy Anaerobic Pond technology

Project Location
Tây Ninh, Vietnam